Thumb

PIPING ERECTION & FABRICATION WORKS FOR HEC LBO PROJECT

LOCATION: Etisalat Facility Management
STATUS: On Going
SCOPE: Transportation, Erection, Testing & Pre-Commissioning of Civil works, Electrical work and Up Grading 3G to 4G Net working in Hole UAE.

WORK GROUPS: FABRICATION & ERECTION
  • Piping
  • Structure
  • Civil
  • Electrical
  • Up Grading 3G to 4G
Thumb

PIPING ERECTION & FABRICATION WORKS FOR HEC LBO PROJECT

LOCATION: TAKREER RUWAIS REFINERY
STATUS: Completed
SCOPE: Transportation, Erection, Testing & Pre-Commissioning of piping works in Unit 103 for HEC LBO Project. Fabrication & Installation of pipe supports.

WORK GROUPS: FABRICATION & ERECTION
  • Piping
  • Structure

Thumb

Temp Support Services for Maintenance Workshop (Fabrication of “F” Keys ) – Habshan-5

LOCATION: GASCO, HABSHAN
STATUS: Completed
SCOPE: Fabrication of "F" Keys

WORK GROUPS: FABRICATION
  • Piping
  • Structure
Thumb

Supply & Compaction of Gatch on Wellheads & Pipeline Berm Construction (79kms)

LOCATION: ADCO, ASAB
STATUS: Completed
SCOPE: Supply of Gatch Material at Wellheads & Pipe line.
Compaction of Gatch at well heads (38 nos.).
Construction of Berm on 79km pipeline in ASAB.

WORK GROUPS: CONSTRUCTION
  • Civil Works
  • Earthworks

SUPPLY
  • Material

Thumb

Civil & Structure Works for Unit 719

LOCATION: SHAH
STATUS: Completed
SCOPE: Excavation of Back fill , lean & reinforced concreting , grouting , concrete protection works .
Installation of 277 Tons of Structural Steel.
Installation of Grafting, ladders , platforms , Hand rails
Supply & Installation of Fence & Gates.

WORK GROUPS: CONSTRUCTION
  • Civil Works

SUPPLY
  • Material
Thumb

Architectural Works for IES Build

LOCATION: SHAH
STATUS: Completed
SCOPE: Installation of Vinyl and Acid resistant tiles , Raised floor work , Exterior and Roof Cladding Panels works, Gypsum Water Proof Board at Battery Room, Corrosion Resistant Painting works, Gypsum Dry Water Proof Board at Telecom, Switch gear and Air LOCL Room, Galvanized Removal Steel Mesh Wall at Cable Basement in IES, Plaster Finish & Painted wall, Painted Gypsum Board , False Ceiling Works, Doors, Exhaust Fan, Rain Water Down Spout Pipe. Constructing the Concrete Block and Concrete Steps.

WORK GROUPS: CONSTRUCTION
  • Civil Works
  • Earthworks

SUPPLY
  • Material

Thumb

Supply of Installation of Fence with associated Civil Works at ASAB Wellheads

LOCATION: ADCO, ASAB
STATUS: On Going
SCOPE: Excavation of Back fill , lean & reinforced concreting , grouting , concrete protection works .
Installation of 277 Tons of Structural Steel.
Installation of Grafting, ladders , platforms , Hand rails
Supply & Installation of Fence & Gates.

WORK GROUPS: CONSTRUCTION
  • Civil Works

SUPPLY
  • Material
Thumb

CONSTRUCTION OF TEMPORARY FACILITIES (CAMP) FOR THE PROJECT OF EPC FOR SPIKING COMPRESSOR

LOCATION: ADCO, SHAH
STATUS: Completed
SCOPE: Site Preparation, Supply and installation of Fence & Gates,
Construction of internal roads (both asphalt and Gatch top), walkways, parking area, DG room, Football ground, Electrical System, Foundation of STP and auxillaries, sewage network system, Fire alarm system, Fire fighting system, Water network system, Area Lighting, Foundations for all Portacabins & Water storage tank

WORK GROUPS: FABRICATION
  • Piping
  • Structure
Thumb

Supply & Compaction of Gatch on Wellheads & Pipeline Berm Construction (79kms)

LOCATION: ADCO, ASAB
STATUS: Completed
SCOPE: Supply of Gatch Material at Wellheads & Pipe line.
Compaction of Gatch at well heads (38 nos.).
Construction of Berm on 79km pipeline in ASAB.

WORK GROUPS: CONSTRUCTION
  • Civil Works
  • E & I

SUPPLY
  • Material
Thumb

CONSTRUCTION OF TEMPORARY FACILITIES (CAMP) FOR PROJECT AT ASAB

LOCATION: ADCO, ASAB
STATUS: Complated
SCOPE: Supply and installation of Fence & Gates.
Walkway parking area, DG room, Electrical System, Foundation of STP and auxillaries, sewage network system, Fire alarm system, Fire fighting system, Water network system, Area Lighting, Foundations for all Portacabins & Water storage tank, Fabrication, Warehouse & Workshops.

WORK GROUPS: CONSTRUCTION
  • Civil Works

SUPPLY
  • Material


Thumb

MIRFA TO RUWAIS PIPELINE FOR NITROGEN SUPPLY

LOCATION: MIRFA, RUWAIS
STATUS: Complated
SCOPE: Supply and installation of Fence & Gates.
Walkway parking area, DG room, Electrical System, Foundation of STP and auxillaries, sewage network system, Fire alarm system, Fire fighting system, Water network system, Area Lighting, Foundations for all Portacabins & Water storage tank, Fabrication, Warehouse & Workshops.

WORK GROUPS: CONSTRUCTION
  • Civil Works
  • Earthworks

SUPPLY
  • Material
Thumb

FEED GAS IMPROVEMENT PROJECT

LOCATION: GASCO, HABSHAN
STATUS: Complated
SCOPE: Piping fabrication, erection, painting, insulation, radiography, PWHT and electrical works

WORK GROUPS: FABRICATION
  • Pipings
  • Erections

CONSTRUCTION
  • Mechanical Works
  • E & I

Thumb

CONSTRUCTION OF TEMPORARY FACILITIES (CAMP) FOR THE PROJECT OF EPC FOR SPIKING COMPRESSOR

LOCATION: ADCO, SHAH
STATUS: Complated
SCOPE: Site Preparation, Supply and installation of Fence & Gates,
Construction of internal roads (both asphalt and Gatch top), walkways, parking area, DG room, Football ground, Electrical System, Foundation of STP and auxillaries, sewage network system, Fire alarm system, Fire fighting system, Water network system, Area Lighting, Foundations for all Portacabins & Water storage tank.

WORK GROUPS: CONSTRUCTION
  • Civil Works
  • E & I

SUPPLY
  • Material
Thumb

BOROUGE 3 UTILITIES & OFFSITES PROJECT RCC BUILDING WORKS

LOCATION: BOROUGE 3, RUWAIS
STATUS: Complated
SCOPE:Area preparation and construction of RCC Frame structure for buildings including rebar, shuttering system, concreting, water proofing, block works, excavation.

WORK GROUPS: FABRICATION
  • Civil
  • Eearthworks
  • Infrastructure

Thumb

DESLUDGING AND CLEANING WORKS

LOCATION: TAKREER, ABU DHABI
STATUS: Complated
SCOPE: Desludging and Cleaning of various Equipments in Takreer Umm Al Nar Refinery. Blinding / Opening / Cleaning / Desludging of Vessels, API separators, Storage tanks, etc.

WORK GROUPS: SERVICES
  • Maintenance
  • Shutdown
Thumb

Bottom Plate Replacement of Steam Condensate Tank

LOCATION: GASCO, HABSHAN
STATUS: Complated
SCOPE:Bottom Plate Replacement with Re-installation of Cathodic Protection System of Steam Condensate Tank at GASCO Habshan Plant -UAE.
Supply, fabrication and erection of tank bottom plate of steam condensate storage tank, including complete design, supply and installation of cathodic protection system.

WORK GROUPS: FABRICATION
  • Piping
  • Structure
  • Erection

SERVICES
  • Maintenance
  • Shutdown

Thumb

DISMANTLING, TRANSPORTATION, REINSTALLATION & COMMISSIONING OF 5000RT MODULAR PLANT

LOCATION: TABREED-AL RAHA ABU DHABI
STATUS: Complated
SCOPE: Dismantling, Relocation, Installation & Commissioning of Cooling Towers, piping spools, chiller skids 2 Nos (70 ton each), steel structure (32 ton), water storage tanks, fence, gates, porta cabins and interlocking tiles. Activities including piping fabrication & erection / steel structure erection / hydrotesting / chemical cleaning / installation of 11kv cables / termination / hi-pot testing / asbuilt drawings etc.

WORK GROUPS: FABRICATION
  • Piping
  • Structure
  • Erection

CONSTRUCTION
  • Mechanical Works
  • Civil Works
  • E & I
  • Infrastructure
Thumb

OIL SEPARATION PLANT

LOCATION: ABU DHABI
STATUS: Complated
SCOPE:Supply of Manpower including suitable qualified welders , fitters, fabricators (experienced in oil field/refinery piping), supervision , planning, scheduling & Execution of the process skids & interconnecting piping between all skids, Tank farm, cooling tower, boiler house and process area which includes Fabrication ,fitting and Erection of Steel Structure, Plant piping & pipe supports including all valves pumps & other fittings, pipe racks & support . Erection of Skids, Equipments and installation of Fire water network. Construction of Foundations, drainage network, pavements etc.

WORK GROUPS: FABRICATION
  • Piping & Erection
  • Steel Structure

CONSTRUCTION
  • Civil Works

SUPPLY
  • Man Power